N 102nd St/Aurora Ave N Pedestrian Bridge Seismic Retrofit
Updated October 22, 2024
What's Happening Now?
Construction to help the N 102nd St/Aurora Ave N Pedestrian Bridge better withstand earthquakes is ongoing. Crews have implemented the final stage of phase one lane closures. One northbound lane of Aurora Ave N is closed between N 100th St and N 103rd St with traffic shifted to the west and two lanes of travel open in each direction. We will be sharing information about phase two lane closures in the coming weeks, as we approach the end of phase one. Sign up for email updates to be notified when additional information is published!
As a reminder, to complete the work as safely and efficiently as possible, the bridge will be closed to people walking, biking, and rolling for the duration of construction (5-6 months). In addition, we will be closing car lanes under the bridge on Aurora Ave N in phases to divert people driving away from where work is occurring. Aurora Ave N is currently reduced to two lanes in each direction below the bridge, with car traffic shifted to the west. At least one lane of travel in each direction will be maintained throughout each phase.
To receive project updates, sign up to join our project listserv.
Project overview
Earthquakes could have a major impact on Seattle’s infrastructure. To address seismic risks to city infrastructure, the City of Seattle established a bridge seismic program to assess how vulnerable the City’s bridges were to earthquakes, and to retrofit bridges to better withstand the potential impacts of an earthquake.
As part of the Levy to Move Seattle, 16 bridges were selected for seismic retrofits, including the N 102nd St/Aurora Ave N Pedestrian Bridge. The N 102nd St/Aurora Ave N Pedestrian Bridge is an older bridge constructed prior to the modernization of the seismic design code. The bridge provides a more direct connection across Aurora Ave N for the Greenwood and Licton Springs neighborhoods.
We're not planning on changing the current use and operation of the bridge. The planned seismic retrofits to the N 102nd St/Aurora Ave N Pedestrian Bridge include several modifications to strengthen existing bridge components and reduce the bridge’s vulnerability to earthquakes. The following are major construction elements:
- Enlarging the bridge cross-section and installing carbon fiber wrapping to strengthen the bridge's superstructure
- Separating the main span from the ramp and the staircase by adding new expansion joints
- Constructing a lightweight fill/wall support system for the ramp
- Constructing a wall/footing support system for the staircase
What to expect during construction
Construction began in June 2024 and is anticipated to last approximately 5-6 months. We will continue to share information on our webpage and through regular email updates. You can sign up online to receive email updates.
To complete the work as safely and efficiently as possible, the bridge will be closed to all people walking, biking, and rolling for the duration of construction. In addition, we will be closing car lanes under the bridge on Aurora Ave N in phases to divert people driving away from where work is occurring. At least one lane of travel in each direction will be maintained throughout each phase.
We understand these closures will impact everyone who uses the bridge and Aurora Ave N regularly and will do what we can to minimize impacts. The phases will include the following closures:
Phase One
Our first phase of lane closures began in mid-June 2024. One northbound lane of Aurora Ave N is currently closed between N 100th St and N 103rd St with traffic shifted to the west and two lanes of travel open in each direction.
Phase Two
As we near the end of phase one lane closures, we will be sharing details about the upcoming phase two lane closures in the coming weeks. Sign up for email updates to be notified when additional information is published and check back here to learn more!
In addition to the above phases of lane closures, we currently anticipate the following construction impacts:
- Work in the public right-of-way near your home or business
- Temporary sidewalk and crossing closures for people walking and rolling. Detours will be provided and signed
- Temporary side street closures. Detours will be provided and signed
- *Side street closure includes 102nd Avenue
- Temporary on-street parking restrictions, with "no park" signs placed 72 hours in advance
- A full closure of the bridge during construction. We will notify nearby homes at least two weeks in advance and again 72 hours before the closure.
- Staged construction equipment and materials as well as noise, dust, and vibrations in the work area
- Typical weekday work hours of 7 AM – 5 PM, Monday through Friday
Project schedule*
30% Design | Complete |
60% Design | Complete |
90% Design | Complete |
Final Design | Complete |
Construction Begins | June 2024 |
* The schedule is subject to change.
Construction began in June 2024 and is scheduled to last approximately 5-6 months. Construction schedules are also subject to change and depend on factors such as weather and availability of crews and materials.
Funding
The project is funded through the Levy to Move Seattle. Approved by voters in 2015, the 9-year, $930 million Levy to Move Seattle provides funding to improve safety for all travelers, maintain our streets and bridges, and invest in reliable, affordable travel options for a growing city.
Get Involved
We're committed to keeping you informed and working with neighbors to limit construction impacts to the extent feasible. Here are some ways to get more information about the project:
- Sign up for our project listserv to receive weekly project updates
- Email the project team at BridgeSeismicRetrofit@seattle.gov
- Leave a voicemail at (206) 775-8734. A project representative will return your call.
Materials
Translation and interpretation
If you need this information translated, please call (206) 775-8734.
如果您需要此信息翻譯成中文 請致電 (206) 775-8734.
Kung kailangan mo ang impormasyon na ito na nakasalin sa Tagalog mangyari lamang na tumawag sa (206) 775-8734.
Si necesita traducir esta información al español, llame al (206) 775-8734.
Odeeffannoon kun akka siif (206) 775-8734.
Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt xin gọi (206) 775-8734.
የዚህን መረጃ ትርጉም ከፈለጉ፣ በዚህ ስልክ ቁጥር ይደውሉ፡ (206) 775-8734.
ናይዚ ሓበሬታ ትርጉም እንተደሊኹም፣ በዚ ቁጽሪ ስልኪ ይድውሉ፡ (206) 775-8734.
당신이 번역이 정보를 필요로하는 경우에, (206) 775-8734? 전화 해주십시오.