Lincoln Park South Play Area Renovation
Updated: June 6, 2023
Spring 2023
The bid advertisement for construction for this project was posted on May 31, 2023. The bid set includes the play equipment replacement at Westcrest Park. Both projects will be constructed by the same contractor. The bid opening is June 21, 2023. We anticipate construction will start in late summer, and complete by end of the year.
Location
Lincoln Park, 8011 Fauntleroy Way SW, 98136
Budget
Seattle Park District provides $600,000 for planning, design and construction.
Schedule
Design: Spring 2021 - Spring 2022
Bid Advertisement: Spring 2023
Construction: Summer 2023 - Winter 2023/2024
Project Description
This improvement project is funded by the Seattle Park District. The play area renovation will update play equipment with play structures accessible to children of all ages and abilities. Additionally, accessibility improvements that meet the standards from the Americans with Disabilities Act (ADA) will be made throughout the play area.
Community Participation
Public Meeting 11/29/2017
Public Meeting 1/24/2018